An organization is starting a PMO. For the initial phase, the PMO director has decided to roll out the use of project charters. As a project manager, why would you be encouraged by this plan?
A
The project charter allows you to establish the business need for the project.
B
The project charter ensures that a preliminary budget and schedule are developed.
C
The project charter authorizes you to use organizational resources to accomplish the objectives of the project.
D
The project charter allows you to get senior management buy-in for your project management approach.