Which statement best describes the proper way to develop the initial project schedule?
A
Create a new MS Project file, enter key deliverables, enter start and end dates for each, and assign resources.
B
Create a new MS Project file, enter the WBS structure and work packages, break down work packages into activities, enter the estimated duration and resource assignments for each activity, and enter the logical dependencies between the activities and work packages
C
Create a new MS Project file, enter the WBS structure and work packages, break down work packages into activities, enter start and end dates for each activity, and compress the schedule to meet the deadline.
D
Find an MS Project file with a proven WBS and activity list template, review the estimated duration and resource assignments for each activity, and review the logical dependencies between the activities and work packages.