Întrebarea 1 din 10
During the Identify Risks process, a project manager made a long list of risk identified with all the stakeholders using various methods. He then made sure that all risks were understood and that triggers had been identified. Later, in plan risk responses, he took all the risks identified by the stakeholders and determined ways to mitigate them. What has he done wrong?